Perencanaan Penjadwalan Perawatan Alat Berat Mobile Crane Menggunakan Metode CPM (Studi Kasus : PT. Menara Riau Perkasa)

  • Rozar Rayendra Universitas Muhammadiyah Riau
  • Dedi Dermawan Universitas Muhammadiyah Riau
  • Muhammad Qurthuby Universitas Muhammadiyah Riau
  • Faradila Ananda Yul Universitas Muhammadiyah Riau
  • Viona Aulia Rahmi Universitas Muhammadiyah Riau
  • Indria Olyvhia Sinatra Universitas Muhammadiyah Riau
Keywords: CPM, Maintenance, Optimizing, Scheduling, Mobile Crane

Abstract

PT Menara Riau Perkasa is a company engaged in the rental of heavy equipment. The maintenance process unscheduled mobile crane heavy equipment is quite long within 5 days including overtime and rest hours and 1 day is inspection. Ordering heavy equipment for 6 days so that the company is often in a hurry for the maintenance process. Therefore, optimization of mobile crane maintenance is carried out by measuring the duration of each maintenance process using the Critical Path Method (CPM). This method is used to identify tasks needed in completing the project and determine scheduling flexibility. This method can complete the maintenance process with an effective time of 2.8 days with 8 hours of operation without rest hours and inspection for 1 day so that the total completion is 3.8 days. The use of the CPM method can reduce the maintenance process time because there are 2 main maintenance process activities that can be done at once with limited leeway time for the battery water process and hydraulic repairs.

  1.  

Downloads

Download data is not yet available.

Author Biographies

Rozar Rayendra, Universitas Muhammadiyah Riau

Program Studi Teknik Industri, Fakultas Teknik

Dedi Dermawan, Universitas Muhammadiyah Riau

Program Studi Teknik Industri, Fakultas Teknik

Muhammad Qurthuby, Universitas Muhammadiyah Riau

Program Studi Teknik Industri, Fakultas Teknik

Faradila Ananda Yul, Universitas Muhammadiyah Riau

Program Studi Teknik Industri, Fakultas Teknik

Viona Aulia Rahmi, Universitas Muhammadiyah Riau

Program Studi Teknik Kimia, Fakultas Teknik

Indria Olyvhia Sinatra, Universitas Muhammadiyah Riau

Program Studi Teknik Industri, Fakultas Teknik

References

N. F. Pangestu, A. F. Zahra dan S. Sutrisno, “Penerapan Metode Critical parth method (CPM) dalam Proyek Pembangunan Jembatan Alun - Alun Kota Kuningan,” J. Ind. Manuf. Eng., vol. 5, pp. 100-106, 2021.

J. Yang, Bin dan C. K. Kao, “Critical path effect based delay analysist method for construktion projects,” pp. 385-397, 2012.

L. R. Lubis, Z. F. Umari, K. Kristi dan A. Akhirini, “Analisis Penjadwalan Waktu Menggunaan Metode Cpm dan Pert. pada Pembangunan gudang Dexa Medica Palembang,” J. Tek. Sipil LATERAL, vol. 1, no. 2, pp. 21-30, 2023.

S. Perdana dan A. Rahman, “Penerapan Manajemen Proyek dengan Metode CPM (Critical Path Method) pada Proyek Pembangunan SPBE,” Amaliah Jurnal Pengabdian Kepada Masyarakat, pp. 242-250, 2019.

Y. Takakura, T. Yajima, Y. Kawajiri dan S. Hashizume, “Application of critical path method to stochastic processes with historical operation data,” Chem. Eng. Res. Des, vol. 149, pp. 195-208, 2019.

M. H. Hasyim, S. E. Unas dan Widiarsa, “Penjadwalan Proyek Konstruksi dengan Metode Flash (Fuzzy Logic Application for Schedulling),” J. Tek. Pangair. J. Water. Resour. eng, p. Vol. 2 no. 1, 2012.

A. C. Siregar dan I. Ifiginia, “Penggunaan critical path method (CPM) untuk evaluasi waktu dan biaya pelaksanaan proyek,” Tek. J. Sains dan Teknol., vol. 15, no. 2, p. 102, 2019.

N. M. Astari, A. M. Subagyo dan K. Kusnadi, “Perencanaan Manajemen Proyek dengan Metode CPM (Critical Path Method) dan pert (Program Evaluation and Review Technique),” Konstruksi, vol. 13, no. 1, p. 164, 2021.

S. H. Sahir, Metodologi Penelitian., Medan: KBM Indonesia, 2022.

R. Rayendra, M. Qurthuby dan I. N. Sari, “Analisis Pengendalian Inventory Filter pada Mesin Genset Menggunakan Metode POQ di PT. Besmindo Materi Sewatamp,” J. Surya. Tek., vol. 10, no. 1, pp. 644-650, 2023.

Mahdiyah, “Perumusan Masalah Penelitian,” Stud. Mandiri dan Semin. Proses. Penelit., pp. 1-32, 2015.

Published
2024-12-31
How to Cite
Rozar Rayendra, Dedi Dermawan, Muhammad Qurthuby, Faradila Ananda Yul, Viona Aulia Rahmi, & Indria Olyvhia Sinatra. (2024). Perencanaan Penjadwalan Perawatan Alat Berat Mobile Crane Menggunakan Metode CPM (Studi Kasus : PT. Menara Riau Perkasa). Jurnal Surya Teknika, 11(2), 536-543. https://doi.org/10.37859/jst.v11i2.8262
Abstract views: 96 , *.pdf downloads: 88