Analisa Produktivitas Excavator di Area PIT 2 Swakelola Tambang Banko Barat PT Bukit Asam, Tbk

  • Muhammad Abdul Ghony Akademi Komunitas Industri Pertambangan Bukit Asam
  • Aristo Akademi Komunitas Industri Pertambangan Bukit Asam
  • Sarmidi Akademi Komunitas Industri Pertambangan Bukit Asam
Keywords: coal, excavator, loading, overburden, productivity

Abstract

A good coal mining process is assessed by productivity and efficiency. Productivity can also be increased by using heavy equipment accompanied by competent operators. As one of the largest coal mining companies in Indonesia, PT Bukit Asam, Tbk is required to always be at the best performance, including at the heavy equipment operator level. This research aims to determine the factors of heavy equipment use as assessed by cycle time on coal productivity. Productivity is limited to the overburden loading process by the Komatsu PC3000SE excavator at PIT 2 Swakelola Tambang Banko Barat. The greatest productivity obtained was 1099 m3 per hour and the average percent productivity was 79.4%. In this research, a match factor of 0.8 was also obtained as a basis for further research that needs to be carried out to optimize the overburden loading and dumping process for PT Bukit Asam

Downloads

Download data is not yet available.

References

J. N and K. R. I. Merang. Dampak Pertambangan Batubara Dalam Kehidupan Sosial Ekonomi Masyarakat di Desa Apung Kecamatan Tanjung Selor Kabupaten Bulungan. Jurnal Ilmu Administrasi Negara (JUAN), vol. 8, no. 2, pp. 111–121, Dec. 2020, doi: 10.31629/juan.v8i2.2679.

Kementerian energi dan sumber daya mineral. Road Map Pengembangan dan Pemanfaatan Batubara. Jakarta, 2021. Accessed: Dec. 14, 2023. [Online]. Available:https://www.minerba.esdm.go.id/upload/ebook/20220329144914.pdf

Yanto. Determinan Ekspor Batubara Indonesia. Prosiding Seminar Nasional Seminar Akademik Tahunan Ilmu Ekonomi dan Studi Pembangunan, vol. 5, pp. 220–225, 2022.

Subowo G. Penambangan Sistem Terbuka Ramah Lingkungan dan Upaya Reklamasi Pasca Tambang untuk Memperbaiki Kualitas Sumberdaya Lahan dan Hayati Tanah. Jurnal Sumberdaya Lahan, vol. 5, no. 2, pp. 83–94, 2011.

Ronald Martin Sokop, Tisano TJ Arsjad, and Grace Malingkas. Analisa Perhitungan Produktivitas Alat Berat Gali-Muat (Excavator) Dan Alat Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea. Jurnal Tekno, vol. 16, no. 70, pp. 83–88, 2018.

Nurnilam Oemiati, Revisdah, and Rahmawati. Analisa Produktivitas Alat Gali Muat dan Alat Angkut pada Pengupasan Lapisan Tanah Penutup (Overburden). vol. 6, no. 3, pp. 194–207, Jun. 2020.

rochmanhadi. Alat-alat berat dan penggunaanya. 1st ed. Jakarta: Badan Penerbitan Pekerjaan umum, 1989. Accessed: Dec. 15, 2023. [Online]. Available:https://lib.ui.ac.id/detail.jsp?id=20356270

Mohammad Fadli S. Faktor Efisiensi Alat-Alat Mekanis dan Faktor Koreksi Bucket. Jakarta, 2020.

B. Sağlam and Ö. H. Bettemir. Estimation of duration of earthwork with backhoe excavator by Monte Carlo Simulation. Journal of Construction Engineering, Management & Innovation, vol. 1, no. 2, pp. 85–94, Jun. 2018, doi: 10.31462/jcemi.2018.01085094.

M. Deri Frasetia and T. G. Saldy. Peningkatan Kapasitas Produksi Alat Angkut Untuk Mencapai Target Produksi 5000 ton/bulan Pada Kegiatan Galian Clay Menggunakan Metode antrian pada Tambang IUP OP Jumaidi, Gunuang Sariak, Sumatera Barat. Jurnal Bina Tambang, vol. 8, no. 1, 2023.

Rochmanhadi. Alat-alat berat dan penggunaannya. 1st ed. Jakarta: Badan Penerbit Pekerjaan Umum, 2003. Accessed: Dec. 15, 2023. [Online]. Available:https://lib.ui.ac.id/detail.jsp?id=20356270

Rezky Anisari. Keserasian Alat Muat dan Angkut untuk Kecapaian Target Produksi Pengupasan Batuan Penutup pada PT. Adaro Indonesia Kalimantan Selatan. Jurnal Poros Teknik, vol. 4, no. 1, pp. 19–23, 2012, Accessed: Dec. 15, 2023. [Online]. Available:https://media.neliti.com/media/publications/126524-ID-keserasian-alat-muat-dan-angkut-untuk-ke.pdf

Abdul Khair, Agus Triantoro, Riswan, and Wahyu Nur Hidayat. Evaluasi Pencapaian Target Produktivitas Alat Gali Muat dan Alat Angkut pada Aktivitas Pemindahan Overburden di PIT1 Blok15 PT Rimau Energy Mining, Site Putut Tawuluh. Jurnal HIMASAPTA, vol. 4, no. 1, pp. 17–24, Accessed: Dec. 15, 2023. [Online]. Available:https://ppjp.ulm.ac.id/journals/index.php/jhs/article/view/474/472

Published
2023-12-26
How to Cite
Ghony, M. A., Aristo, & Sarmidi. (2023). Analisa Produktivitas Excavator di Area PIT 2 Swakelola Tambang Banko Barat PT Bukit Asam, Tbk . Jurnal Surya Teknika, 10(2), 880-885. https://doi.org/10.37859/jst.v10i2.6430
Abstract views: 74 , *.pdf downloads: 94